Phase 1, 2, and 3 (N. Trail from 14th St to Dr. MLK Jr. and 16th St from N. Trail to Cocoanut Ave.) – Completed.
Phase 4 (N. Trail from North of Dr. MLK Jr. to South of Myrtle St. Intersection) – Lane Paving scheduled for Monday and Tuesday August 3rd & 4th 2026 – final restoration to follow.
Phase 5 & 7 (N. Trail from Myrtle St to 47th St and 47th St from N. Trail to Rilma Ave) – Certification of New Water Main on-going.
Phase 6 (N. Trail from 47th St to Beverly Dr) – North and Southbound inside lanes closed, temporary paving and lanes to be reopened on Friday, August 8th, 2026. – North and Southbound outside lanes closure TBD.
2. North Lodge Dr Watermain Replacement and Lift Station No. 90 Construction
North Lodge Dr Paving – completed.
New Lift Station construction work on-going.
Coordination with FP&L for new service and connection.