main replacement
  • July 2026 CCNA Utilities Projects Update
  1. North Tamiami Trail AC Water Main Replacement:
  • Final roadway paving at US-41/Dr. MLK Jr Way, US-41/24th St. and Cocoanut Ave/16th St intersections on Thursday night, July 16th.
  • Phase-5 (N. Trail from Myrtle Ave to 47th St) – Northbound and southbound inside lanes to be reopened on Thursday, July 2nd for the holiday weekend.
  • Phase-5 (N. Trail from Myrtle Ave to 47th St) – Northbound and southbound outside lanes to be closed starting on Monday, July 13th.
  • Myrtle St intersection inside lane closure/utility crossing completed on Saturday, June 27th.
  • Myrtle St intersection outside lane closure/utility crossing to be done on Friday, July 17th through Monday, July 20th.
  • Phase 1, 2, and 3 (N. Trail from 14th St to Dr. MLK Jr. and 16th St from N. Trail to Cocoanut Ave.) – Final Completion & Acceptance on Tuesday, July 28th, 2026.
  • Phase-6 (N. Trail from 47th St to Beverly Dr) – Northbound and southbound inside lanes to be closed starting Monday July 20th. – please review attached MOT Plan. Provide comments by Friday, July 10th, 2026.

2.  North Lodge Dr Watermain Replacement and Lift Station No. 90 Construction

  • New Lift Station construction work on-going.
  • Coordination with FP&L for new service and connection

3.  Citywide Small Potable Water Meter Replacement

4.  Sanitary Sewer Lateral Service Lining

  • Work is ongoing.

For all additional utilities project, please visit: Utility Construction Projects | City of Sarasota

Let me know if you have any questions.

Thanks,

Georges Nicolas, M.CE, PE, ENV SP, M.ASCE
Utilities Engineering Manager
Phone: (941) 263-6136
Mobile: (941) 376-4535
Email: georges.nicolas@sarasotafl.gov
1750 12th St. Sarasota, FL 34236

3-27-2026

About Author

What do you feel about this?

Skip to content