The Dredging contractor started equipment mobilization January 8th, 2026.
Dredging will start at cut 3 and start placing sand on the north part of the project area (beginning January 19th)
They will and move along the beach from the north to the south.
Anticipated project completion by April 2, 2026.
The corps will make a total of 5 cuts in the pass, starting at Cut 3. Cut 3 will go from Jan 19-Jan 25 . The Cut 4 will go from Jan 26-Jan 30. Cut 5 will go from Jan 31- Feb 1. These locations have small quantities of sand, so they will move thru quickly. The renourishment will start slowly for the same reason, a small quantity of sand to start with. Cut 2 will run from Feb 2- Feb 24 and lastly Cut 1 will run from Feb 25-March 26. Both of these cuts have much more sand.