June 2026 CCNA Utilities Projects Update

  1. North Tamiami Trail AC Water Main Replacement:
  • Phase 1 & 3 (N. Trail from 14th St to Dr. MLK Jr Way) – punch list for final site restoration is ongoing. Concrete repair, sodding, and cleaning.
  • Phase 2 (16th St from N. Tamiami Trl. to Cocoanut Ave – FDOH certification approved. Final connection and roadway restoration to start 5/29 through 6/05.
  • Construction staging Northwest corner of Dr. MLK Jr Way & N. Tamiami Trl. has been moved.
  • Phase-4 (Dr. MLK Jr Way to Myrtle Ave) – grouting-in-place of the old AC Pipe has been completed. Asphalt and Concrete restoration work to start 6/01.
  • Phase-5 (N. Trail from Myrtle Ave to 47th St) – starting Monday 6/01 both inside lanes NB and SB traffic will be closed. Work will be on-going until 8/17, tentatively.

2.  North Lodge Dr Watermain Replacement and Lift Station No. 90 Construction

  • Small WM replacement has been completed
  • Work has resumed for the new LS#90 construction.
  • Project is scheduled to be substantially completed on 7/11/2026

 

3.  Citywide Small Potable Water Meter Replacement

  • Work is ongoing.

4.  Sanitary Sewer Lateral Service Lining

  • New clean-out installation within the public right-of-way is ongoing.
  • Lining of the Sewer Main will start 6/01.

For all additional utilities project, please visit: Utility Construction Projects | City of Sarasota

Let me know if you have any questions.

Thanks,

Georges Nicolas, M.CE, PE, ENV SP, M.ASCE
Utilities Engineering Manager
Phone: (941) 263-6136
Mobile: (941) 376-4535
Email: georges.nicolas@sarasotafl.gov
1750 12th St. Sarasota, FL 34236

3-27-2026