Phase-1 (US-41 from 14th St to South of MLK Jr): Final connection to the new water main is complete
Phase-2 (Intersection of Cocoanut & 16th Street): Water service connections to new water main to start next week. Complete intersection closure work – TBD
Phase-3 (N. Trail from 17th St to Dr. MLK Jr Way) Final connection to the new watermain is on-going and will be completed in 2 weeks.
Phase-7 (47th St. from N. Trail to North Water Tower Park): The Park is open to the public, but utility work will be ongoing.
North Lodge Dr Watermain Replacement and Lift Station No. 90 Construction
Replacement of an old 3-inch Asbestos Cement Watermain has started and will continue for the month of March complete with a new Lift Station