Utilities Projects Update – February 2026

main replacement

February 2026 CCNA Utilities Projects Update

North Tamiami Trail AC Water Main Replacement:

  1. Phase 1-3 (US-41 from 14th St to South of MLK Jr):
    Final connection (transfer to new watermain) to and from all side streets to start Monday, February 9th, 2026 (No closure on US-41)
  2. Phase-2 (Intersection of Cocoanut & 16th Street):

    Complete intersection closure work tentatively first week of March.

  3. Phase 4 (US-41 from North of MLK Jr Way to South of Myrtle):

    Northbound and Southbound Inside lane work to be completed and paving is tentatively scheduled for this Wednesday, February 4th, 2026.

  4. US-41/MLK Jr Intersection work:  This is a weekend 24-hr operation to minimize regional traffic and business impact. Work to occur February 13th through 15th and February 20th through 22nd.

  5. Phase 7 (47th St. from US-41 to Rilma):
    Work to continue to West of Rilma Ave. throughout this week.

    Intersection of Rilma/ North Entrance of North Water Tower Park (NWTP) to be closed starting Monday, 9th, 2026. North entrance of the NWTP to be reopened ASAP.

    Let me know if you have any questions.

Thanks,

Georges Nicolas, M.CE, PE, ENV SP, M.ASCE
Utilities Engineering Manager
Phone: (941) 263-6136
Mobile: (941) 376-4535
Email: georges.nicolas@sarasotafl.gov
1750 12th St. Sarasota, FL 34236

2-2-2026