Landscape Coordination Plan, click on image for more details
The Florida Department of Transportation (FDOT) has announced project plans for upcoming improvements along SR 789 (Bird Key to Sunset Drive). Construction is anticipated to begin in early 2026 and be completed by early 2027.
Key Improvements:
Extension of bus-only lanes
Sidewalk-level bicycle lanes at Bird Key Drive and Sunset Drive intersections
Dedicated bicycle signals
Drainage upgrades at Sunset Drive and Bird Key Drive intersections
Sunset Drive area: raising roadway approximately 1 foot on average
Bird Key Drive area: raising roadway approximately 8 inches on average
Raising the seawall cap near Sunset Drive by 2 feet to match the adjacent seawall near 660 Golden Gate Point
Shorter pedestrian crossing distances at intersections
Tighter turning radii to slow right-turning vehicles
Lane Closures: Lane closures are anticipated during construction. The current restrictions are as follows:
Weekend lane closures: 9:00 PM – 7:00 AM
Weekday lane closures within 600 ft of intersections: 7:00 PM – 9:00 AM
Weekday open-road lane closures (not near intersections): 9:00 PM – 7:00 AM
Speed limits during construction: remain 35 MPH on both Gulfstream Ave. and John Ringling Causeway (SR 789).